Multiple Choice Question: By what day should the Section 1 work be completed? Pick the best answer:
A. Thursday, September 10, 2020.
B. Wednesday, September 9, 2020.
C. Tuesday, September 8, 2020.
D. Labor Day Monday, September 7, 2020.
E. Sunday, September 6, 2020.
Answer: The correct answer is E or 5 calendar days before the scheduled day to close escrow. Under the default language of the Request for Repair (RR), Section 1 work, including a written termite clearance, must be completed “no later than 5 Days Prior to Close of Escrow” (see paragraph 1(b)(iii) of the RR).
The capitalization of the words, “Days Prior,” in the RR means that the term is contractually defined. Under paragraph 30H of the RPA, “Days Prior” means “the specific number of calendar days before the occurrence of the event specified, not counting the day on which the specified event occurs.” Saturdays, Sundays, and legal holidays are not excluded.
As the listing agent, make sure that your sellers understand the timing requirement for any repairs that they agree to perform. Unless otherwise specified, such repairs must be completed at least 5 calendar days before the scheduled close of escrow date, regardless of whether the fifth day falls on a Saturday, Sunday, or legal holiday.